SE 29th Street Construction getting a head start on Spring

Spotted Photo Gallery

SE 29th Street from to SE Wittenberg Road, east to a point 500’ west of SE Croco Road is being widened from 2 lanes to 5 lanes this summer. Bettis Asphalt is the general contractor on the $8,282,575.19 project. The project is being constructed in 4 phases. Phase I and II were completed in the summer of 2019. Phase III, the north half of the 5 lane section is expected to be complete in July 2020. Phase IV, the south half, has a completion date of December 2020.